EDIT MAIN
Plus_blue
Blaine School District's $45M Capital Projects Bond initiative was approved by voters in the February 2015 Special Election. Our district is privileged to have the opportunity to make much needed improvements to multiple facilities. In the months ahead, we are committed to keeping our constituents informed of the progress that is being made specific to planning for and the delivery of our commitments.

Blaine High School Construction Progress

The first of a three-phase construction project at Blaine High School was completed in the Fall of 2017. During the 2017-18 school year, students and staff have enjoyed the expanded opportunities available in this new facility which includes a high school cafeteria, a small theatre, CTE shop, and additional classroom space.

Phase II, which includes a two-story classroom building connecting Phase I to the Science Building, began in early July 2017. The building was completely dried in by Spring Break, and progress is visible on the exterior finishes. For the remaining weeks of this school year, crews will continue to work on the new building's interior. Phase III, which includes renovation of the library and office areas, is scheduled to begin in June of 2018.

We continue to look forward to students and staff being provided with a safe, responsive, adaptive, and inspiring facility that ultimately serves to support both individual and collective teacher and learner needs and interests. Please look below for additional details on this and other Blaine School District facility improvements.

Monthly Updates to the Board of Directors
May 2015 June 2015 July 2015 August 2015
September 2015 October 2015 November 2015 January 2016
February 2016 March 2016 April 2016 May 2016
June 2016 July 2016 August 2016 September 2016
October 2016 November 2016 January 2017 February 2017
March 2017 April 2017 May 2017 June 2017
July 2017 August 2017 September 2017 October 2017
November 2017 January 2018 February 2018 March 2018
April 2018
BHS Phase 1
The first phase of high school construction was completed in time
for students to arrive at the beginning of the 2017-18 school year.
BHS Phase 1 Collage
The high school's Phase 1 facility includes a small theater,
CTE shops, additional classrooms, a band room, cafeteria,
student lounge, work rooms, and a new staff parking lot.
Tennis Courts
The old tennis courts at BES were resurfaced in July 2017.
BHS Greenhouse
The new high school greenhouse was completed in January 2017.

Playground
A new playground was installed at Blaine Elementary School. (September 2016)
PS Addition
Tiger Construction built the addition to Blaine Primary School during the 2015-16 school year. (Summer 2016)
PS Music Rm
A small covered area on the east side of Blaine Primary School was converted into a dedicated music room. (Summer 2016)
PS Roof
The roof on the existing Blaine Primary School facility was replaced. (Summer 2016)
PS Playshed
The Blaine Primary School's covered play area was enclosed. (Summer 2016)
PRPS Playground
A new playground was installed at Point Roberts Primary School. (Fall 2015)
Roof
Roofing projects were completed at both Blaine Middle School (Western Roofing Company) and Point Roberts Primary School (Hytech Roofing). (Summer 2015)
PS Playground
Northwest Playground Equipment, Inc installed the new Primary School playground. (Summer 2015)
ES Carpet
Beresford Company installed new carpet and vinyl flooring at the Elementary School. (Summer 2015)
HS Track
Beynon Sports Surfaces completed the work of repairing the base and replacing the surface of the High School track. (Summer 2015)
MS Lot
The Middle School Gym parking lot was replaced by Colacurcio Brothers Construction Co. (Summer 2015)
Central Lot
All campus parking lots were re-striped. (Summer 2015)