Capital Projects Information

Blaine School District values the support of our community in making improvements to our campus facilities. Voters approved a Capital Projects Bond in 2015, as well as a Technology and Capital Projects Levy in 2018. Our district is privileged to have the opportunity to make much needed improvements to multiple facilities with these resources. We are committed to keeping our constituents informed of the progress that is being made specific to planning for and the delivery of our commitments. 

Click here to view a list of monthly updates reported to the Board of Directors.



Blaine High School Construction Progress

Core Facility: Spee West Construction broke ground on Phase I of the High School project in July 2016. Phase II began in July 2017. The third and final phase is now underway.

Phase I: The first phase of construction was completed in the Fall of 2017. Since that time, students and staff have enjoyed the expanded opportunities available in this new facility which includes a cafeteria, small theater, CTE shops, and additional classroom space. Due to the expanded need for office space, plans are underway to convert the existing student lounge area to offices. A new parking lot was also added on the south side of campus. 

Phase II: Occupancy was approved in time for the arrival of students at the start of the 2018-19 school year, and they have been enjoying the modern classrooms in this new two-story facility. 

Phase III: Demolition in the summer of 2018 cleared out an area that will become the center courtyard of the high school campus. Renovation work is now underway on the library, offices, and east-side classroom areas. During this final phase of construction, the library and administration offices are temporarily housed in the Phase I building. 

Grandstand: The District’s construction team is continuing to review cost estimates (separately) for both the seating area as well as the overall grandstand structure. More definitive plans for both components of the project are anticipated in November.

Completed Projects


BLAINE HIGH SCHOOL

BHS Track Replacement

The track was repaired and resurfaced in the summer of 2015.

BHS Greenhouse

The new greenhouse was completed during the winter of 2017.

BHS Tennis Courts

New tennis courts were completed in the summer of 2017.

BHS New Facility - Phase 1 and Phase 2

The first phase of the High School project was completed in the fall of 2017, and the second phase was completed in the fall of 2018.

BLAINE PRIMARY SCHOOL

BPS Playground

New playground equipment was installed in the summer of 2015.

BPS Play Shed

The large covered play area was enclosed in the summer of 2016.

BPS Music Room

A small covered area was converted into a new music room in the summer of 2016.

BPS Roof Replacement

The existing roof was repaired and replaced in the summer of 2016.

BPS New Classroom Pod

Blaine Primary School's additional classroom wing was completed in the summer of 2016.




BLAINE ELEMENTARY SCHOOL

BES New Carpet and Flooring

Carpet and vinyl flooring was installed in the summer of 2015.

BES Playground

New playground equipment was installed in September of 2016.

BES Play Shed and Classroom Remodel

Classroom and play shed remodel completed in September 2018.

CAPITAL MAINTENANCE AND OTHER IMPROVEMENTS 

Parking Lot Resurfaced

The Middle School Gym Parking Lot and the fire lane along the west side of the PAC were resurfaced in the summer of 2015.

Center Parking Lot Restriped

Re-striping of all campus parking lots was done in the summer of 2015.

Point Roberts Primary School Roof

Roofing projects at both Blaine Middle School and Pt. Roberts Primary School were completed in the summer of 2015.

Point Roberts Primary School Playground

Installation of the new playground at Point Roberts Primary School was completed in October 2015.

BES Tennis Courts Resurfaced

The old tennis courts at Blaine Elementary School were resurfaced in July 2017.

Replacement of existing door locking systems in the Primary, Elementary, and Middle Schools was completed in the summer of 2018, including cameras at key entry points to facilitate remote operation.

  • The upgrade of the District-wide intercom, clocks, and bell system was completed in February 2017.
  • Seismic improvements to the Middle School gym completed in August 2018.